Home > Case Studies > Overcoming Complex Platform Challenges

Overcoming Complex Platform Challenges

A windfarm in the sunset

A mixed platform project of 18 x 2.3MW and the first installation in the US of 48 x 4.5MW turbines. Stretching over 24,000 acres, 3,000ft above sea level on the high plains of New Mexico.

The larger turbines involved a split-phased pre-assembly of the nacelle components due to size and weight: a separate three-section drive train and a three-section tower.

Challenge 

  • Managing the simultaneous installation of two different turbine types involving two sets of RAMS and Energy Isolation Procedures
  • The installation company’s technicians had not received any training on this new tower type
  • The engineering proposal for the platform’s installation and troubleshooting had not been tested
  • Inherent production faults were identified within the product
  • The location, environment and weather could affect the success of the project

Solution

Working as one-team with the customer, we established a number of processes to tackle these challenges:

  • Conducted the platform-specific RAMS and energy isolation training
  • Delivered the installation process training to the technicians including coaching, mentoring and on-the-job training
  • Oversaw the installation via our Technical Field Advisors and Supervisors
  • Problem resolution using local engineering supply chain and supporting the engineering process through lessons learned
  • Developed the retro-fit campaign
  • Specific PPE provided that supported the technicians whilst exposed to the environment.
  • Emergency response plan was enhanced to account for the local wildlife

Results

  • The project was closed out to client satisfaction
  • Lessons learnt fed back through the customers engineering department for concurrent and future projects
  • Following this project, we were invited to complete further installation projects with the customer across North America
  • 122 retro-fits per tower were identified and completed.